What is the difference between factory acceptance test and site acceptance test?

What is the difference between factory acceptance test and site acceptance test?

The factory acceptance tests are done at the vendor factory site, to make sure that certain requirements are met. Site acceptance tests are done at the worksite and its acceptance leads to the plant start-up.

What is factory acceptance test?

What Is Factory Acceptance Testing? Factory Acceptance Testing (FAT) helps verify that newly manufactured and packaged equipment meets its intended purpose. The FAT validates the operation of the equipment and makes sure the customers’ purchase order specifications and all other requirements have been met.

Which testing is onsite acceptance test?

Site Acceptance Testing (SAT) provides an opportunity for final confirmation that the performance experienced during the Factory Acceptance Testing (FAT) is repeated after the systems are installed onsite, ensuring nothing has changed or was damaged during shipment and installation.

What is the purpose of a factory acceptance test?

What is Factory Acceptance Testing? Factory Acceptance Testing (FAT) is a process that evaluates the sterilizer during and after the assembly process by verifying that it is built and operating in accordance with design specifications.

Which comes first sat or fat?

The SAT is related to the FAT and also entails inspection and dynamic testing of systems or major system components to support the qualification of equipment. The SAT is executed on completion of all commissioning tasks; but prior to the start of Installation Qualification execution.

How can you tell if your fat?

A BMI number is designed to give you an idea of how much body fat you have as a ratio of your weight to height. It’s measured by taking your weight in kilograms and dividing it by your height in meters squared. A reading at or over 30 means you’re obese.

Who is responsible for factory acceptance test?

Sometimes the issues are the manufacturer’s responsibility, e.g. an instrument doesn’t work properly, and other times they are the customer’s responsibility (for example, if a customer decides after seeing the physical layout they want to reconfigure the design, the manufacturer can move things around prior to shipping …

What are the different types of acceptance testing?

Types of Acceptance Testing

  • User Acceptance Testing (UAT) The name itself says that it is from the user point of view.
  • Business Acceptance Testing (BAT)
  • Contract Acceptance Testing (CAT)
  • Regulation Acceptance Testing (RAT)
  • Operational Acceptance Testing (OAT)
  • Alpha Testing.
  • Beta Testing.

How long does a factory acceptance test take?

This test is generally conducted for 60 minutes to ensure the system meets the acceptance criteria.

What is the process in factory acceptance testing?

What are the Process in Factory Acceptance Testing? The main objective of the FAT is to test the safety instrumented system (logic solver and associated software together). The tests are normally executed during the final part of the design and engineering phase before the final installation at the plant.

What does fat stand for in factory acceptance test?

FAT = Factory Acceptance Test Testing of equipment and relevant documentation at the vendor‘s workshops against the requirements of an approved test protocol SAT = Site Acceptance Test Testing of equipment and relevant documentation at the site of use of the equipmentagainst the requirements of an approved test protocol. FAT/SAT – Explanation

Where do you do a site acceptance test?

A site acceptance test is performed at the buyer’s location to verify the equipment’s specifications meet the buyer’s requirements and standards. Replicating and providing all working conditions at the manufacturer’s location isn’t possible, so some SATs can be the same as the factory acceptance test (FAT).

Is the site acceptance and operation qualification testing the same?

It should be noted that the Site Acceptance Testing and the Operation Qualification Testing largely fulfil the same objectives (testing against the Functional Specification) and that these may usefully be performed at the same time or combined.